Electrical equipment rehabilitation plan for the Bécancour smelter's (ABI) rectifier sets
  • LOCATION
    Bécancour, Québec, Canada
  • CLIENT
    ABI
  • PROJECT
    Rehabilitation of the 230 kV sub-station for ABI’s rectifier sets
  • PERIOD
    2005 - 2008
  • DISCIPLINES
    Electrical, instrumentation, civil and mechanical

PROJECT DESCRIPTION

BBA is responsible for planning and carrying out the 230 kV sub-station's rehabilitation project, mainly including electrical installations for ABI's 12 rectifier sets in the Centre-du-Québec region. The BBA team defined requirements, collected and analyzed data, prepared technical specifications for the required equipment, designed new installations, assisted with in-plant testing, and performed all on-site supervision, commissioning and performance testing services, without shut-downs. The scope of work included: 

  • Replacement of major equipment: 12 rectifier transformers (over 110 MVA) and 5 regulating transformers (116 MVA)
  • Replacement and /or renovation of ancillary equipment : 230 kV breakers, 230 kV disconnectors, 230 kV bus expansion joints, 230 kV metering units, 230 kV lightning arresters, RC circuits, rectifiers, 600 V distribution, protection/control circuits, communications system
  • Capacity expansion of the oil recovery system and addition of an oil/water separator;
  • Addition of a 52 kV overhead standby line
  • Addition of air conditioning in technical corridors for each electrolysis set
  • Addition of a make-up cooling system in rectifier rooms
  • Strengthening of the reactive power compensation, including harmonic filters