BBA

Petrochemical

Petro-Canada Refinery Power System Study
  • LOCATION
    Montreal, Quebec, Canada
  • CLIENT
    Petro-Canada
  • PROJECT
    Short-circuit and protective device coordination studies, arc flash analysis
  • PERIOD
    2006-2007
  • DISCIPLINES
    Electrical

PROJECT DESCRIPTION 

Petro-Canada mandated BBA to perform a complete arc flash analysis for its Montréal-East refinery. The main objective of this study was to determine, at different locations, the flash protection boundary within which the worker must wear an appropriate PPE. According to a specific working distance, the category of required PPE was also determined. Prior to the arc flash analysis itself, a short-circuit study and a protective device coordination study were carried out. 

The scope of work for this project consisted of the following:

  • On-site data collection
  • Plant network short-circuit study
  • Protective device coordination study
  • Arc flash analysis